February 17, 2022

December 17, 2021

  • all rough-in inspection completed by Monday, December 20, 2021
  • currently painting MC units and hanging drywall in MC commons

December 10, 2021

  • Completed a couple more rough-in Inspections for 1st Floor Commons and Memory Care Commons.
  • All that is left for rough-ins now is the Main Commons and this is slated for next Friday.

December 3, 2021

  • Rough-in/cover up inspection complete.
  • All exterior paving is complete and backfilling should be complete before next Monday.
  • All that is left to finish on exterior is landscaping and site furnishings which is currently ongoing.

December 2, 2021

November 24, 2021

  • Finalized rough-in inspections on Monday morning for the MC commons corridor and completed RI inspections on 3rd Floor Commons yesterday.
  • MC units are hung and being taped and finished.
  • Progressing along on 3rd floor. As the units get completed the common/corridors should be done as well and we will work our way down and out of the building.

November 19, 2021

  • Main parking lot got striped, the MC units are completely drywalled
  • Rough-ins in AL Corridor commons are in the works and we will be complete with 3rd next Tuesday and starting on 2nd floor.
  • As of right now we are on pace to have the building completely white before we break for Christmas.

October 12, 2021

October 11, 2021

June 3, 2021