- Started wall panel layout and framing at the AL Wing’s A and B.
- Started pouring the SOG at the Memory Support Wing.
- Started videotaping the sanitary lines.
- Finished installing the ComEd transformer pads.
- Finished the field work for the foundation as-built.
- Mini Milestone: With exception to the four (upper) P24 Porte Cochere Piers, all of the foundation work has been completed and backfilled.
- Continued installing the empty conduit sleeves for ComEd’s primary feeders.
- Continued on storm sewer – site utility work.
- Continued the field work for the site utility as-built.
- Continued underground plumbing and electrical underground at the Commons Wing.
- Finished installing the stone sub-base at the entire Memory Support Wing.
- Sanitary Testing with West Dundee/HBK Engineering.
- Passed our Fire Flush Test Inspection with the West Dundee Fire Marshal and West Dundee Public Works.