- 1st Floor Assisted Living corridor and unit bathrooms paint will be complete this week, which will open up work for corridor ACT grid and cabinets in the unit bathrooms.
- In commons building 3rd floor we currently have the floor getting primed and ready for paint. We will move into installing the decorative millwork once the floor gets painted. There is a possibility to install millwork before paint and covering it to avoid overspray.
- 2nd floor commons is currently getting sanded and will be primed mid this week and ready for paint and millwork the following week.
- We are installing the duct work and fire sprinkler work in memory care commons area which will be followed up by drywall framing and ready for cover inspections for secondary lids.
- ACT grid is installed on 2nd and 3rd floor AL building corridors and is currently in process of getting lights installed.
- Carpet on 3rd floor is complete and final punch work is progressing this week.