Glenbrook Report December 3, 2021

  • Moving through inspections and are waiting on a couple more to finish out some areas in prep for drywall install.
  • MEP trades are moving along well in all areas and wall coverings and painting is following closely.
  • We are working on getting landscaping completed yet this year and parking lot striping is going in this weekend on part of the lot.
  • We are getting ready to start install of public area casework and continue on our revised countertop installs.