West Dundee Update, December 14, 2021

  • Started wall panel layout and framing at the AL Wing’s A and B.
  • Started pouring the SOG at the Memory Support Wing.
  • Started videotaping the sanitary lines.
  • Finished installing the ComEd transformer pads.
  • Finished the field work for the foundation as-built.
  • Mini Milestone:  With exception to the four (upper) P24 Porte Cochere Piers, all of the foundation work has been completed and backfilled.
  • Continued installing the empty conduit sleeves for ComEd’s primary feeders.
  • Continued on storm sewer – site utility work.
  • Continued the field work for the site utility as-built.
  • Continued underground plumbing and electrical underground at the Commons Wing.
  • Finished installing the stone sub-base at the entire Memory Support Wing.
  • Sanitary Testing with West Dundee/HBK Engineering.
  • Passed our Fire Flush Test Inspection with the West Dundee Fire Marshal and West Dundee Public Works.